Los Angeles Soft Story Retrofit Program
[vc_row row_height_percent="0" override_padding="yes" h_padding="2" top_padding="3" bottom_padding="3" overlay_alpha="100" gutter_size="3" column_width_percent="100" shift_y="0" z_index="0" row_height_use_pixel=""][vc_column column_width_percent="100" overlay_alpha="50" gutter_size="3" medium_width="0" mobile_width="0" shift_x="0" shift_y="0" shift_y_down="0" z_index="0" zoom_width="0" zoom_height="0"][vc_custom_heading]From past earthquakes, multi-story buildings with weak and/or open front wall lines creating a “soft-story” (i.e. buildings with tuck-under-parking) performed poorly and collapsed.[/vc_custom_heading][vc_column_text]The goal of the mandatory retrofit program, under Ordinance 183893 and Ordinance 184081, is to reduce structural deficiencies by the most economical and feasible method. Without proper strengthening, these vulnerable buildings may be subjected to structural failure during and/or after an earthquake.
Buildings that are most vulnerable have been identified with the following criteria:
- Consist of 2 or more stories wood frame construction
- Built under building code standards enacted before January 1, 1978
- Contains ground floor parking or other similar open floor space
The program does not apply to residential buildings with 3 or less units.
To verify if your building is within the scope,
Please refer to the Permit & Inspection Report (Property Activity Report).
To obtain the inventory list of buildings, please contact
LADBS Custodian of Records
(213) 482-6770
LADBS.custodianofrecords@lacity.org[/vc_column_text][/vc_column][/vc_row][vc_row unlock_row="" row_height_percent="0" override_padding="yes" h_padding="2" top_padding="0" bottom_padding="0" overlay_alpha="100" gutter_size="3" shift_y="0" row_height_use_pixel=""][vc_column column_width_use_pixel="yes" overlay_alpha="50" gutter_size="3" medium_width="0" shift_x="0" shift_y="0" zoom_width="0" zoom_height="0"][vc_gallery el_id="gallery-47626" medias="80317,80318,80319" gutter_size="2" media_items="media,icon" screen_lg="600" screen_md="600" screen_sm="480" images_size="three-two" single_overlay_opacity="50" single_h_align="center" single_padding="2" single_title_dimension="h1" single_icon="fa fa-plus2" single_border="yes" carousel_rtl="" single_title_uppercase=""][/vc_column][/vc_row][vc_row row_height_percent="0" override_padding="yes" h_padding="2" top_padding="3" bottom_padding="0" overlay_alpha="100" gutter_size="3" column_width_percent="100" shift_y="0" z_index="0" row_height_use_pixel=""][vc_column column_width_percent="100" overlay_alpha="50" gutter_size="3" medium_width="0" mobile_width="0" shift_x="0" shift_y="0" shift_y_down="0" z_index="0" zoom_width="0" zoom_height="0"][vc_custom_heading]Each property owner of these buildings will be sent an order to comply. These orders will be sent accordingly based on the following priorities.[/vc_custom_heading][vc_column_text]
Priority | Categories | Start date of Sending Out Orders |
---|---|---|
I. Buildings with 16 or more dwelling units | 3-story and above | May 2, 2016 |
2-story | July 22, 2016 | |
II. Buildings with 3 or more stories | with less than 16 units | October 17, 2016 |
III. Buildings not falling within the definition of Priority I or II | with 9-15 units | July 24, 2017 |
with 7-8 units | August 21, 2017 | |
with 4-6 units | September 25, 2017 | |
Condos/Commercial | November 6, 2017 |
The property owner must comply with the ordinance within the following time limits:
From the receipt of the Order to Comply:
- 2 years: Submit proof of previous retrofit, or plans to retrofit or demolish
- 3.5 years: Obtain permit to start construction or demolition
- 7 years: Complete construction
Reference: LADBS Soft Story Retrofit Program
[/vc_column_text][/vc_column][/vc_row][vc_row row_height_percent="0" override_padding="yes" h_padding="2" top_padding="3" bottom_padding="2" overlay_alpha="100" gutter_size="3" column_width_percent="100" shift_y="0" z_index="0" row_height_use_pixel=""][vc_column column_width_percent="100" overlay_alpha="50" gutter_size="3" medium_width="0" mobile_width="0" shift_x="0" shift_y="0" shift_y_down="0" z_index="0" zoom_width="0" zoom_height="0"][vc_custom_heading]Finding a Soft Story Retrofit Engineer to Trust[/vc_custom_heading][vc_column_text]As noted engineers of distinction and local to the Los Angeles/Southern California area; we recommend ourselves at JN Engineering as exemplary engineers and contractors able to cater to all of your structural needs, especially for all your Soft Story Engineering Needs. To see more information, please check out our Soft Story Services page.